1997-2002
Initial concept studies and several reports were commissioned to assess feasibility of GV Link along with delegation to seek government support
- 1997 Council commenced investigation of the feasibility of developing an intermodal terminal in the region.
- 2001 Report titled Shepparton Freight Hub/Inland Port completed by Logistics Bureau (funded by the then Victorian Department of Infrastructure)
- 2002 Report titled Goulburn Valley Freight Logistics Study Phase 2 undertaken by the Logistics Bureau to study the commercial viability of GV Link with respect specifically to SPC-Ardmona.
2003-2011
Commencement of the planning/design process, land acquisition, and feasibility
- 18 December 2003 Planning Scheme Amendment C34 to facilitate the establishment GV Link (then known as Goulburn Valley Freight Logistics Centre) placed on exhibition
- 2004 Delegation of local industry, Council and government officials visited Canberra to seek Federal support for GV Link
- 15-17 & 24 June 2004 Panel held.
- November 2004 Panel report provided recommending that Planning Scheme Amendment C34 be adopted subject to several recommendations.
- 7 December 2004 Council adopted Amendment C34.
- 5 May 2005 Planning Scheme Amendment C34 approved
- 2005 Council commenced an ‘Expression of Interest’ process aimed at securing a preferred developer for the site.
- 2007 Economic review of the feasibility of developing the site was undertaken.
- 12 December 2008 Development plan and planning application in relation to the subdivision and development of the land issued.
- 2008 Council undertook ‘Expression of Interest’ for the detailed design of the infrastructure/subdivision plan of the site.
- 2009 Landscape design report completed
- 2010 Detailed design plans completed
- 2010 Flood modelling updated
- 2011 Council secured the site, finalised payment for the compulsory land acquisition
- 2013 Economic feasibility review of the GV Link project undertaken
2014 to now
Further review, recent activity, and investor interest
- 2014 Council resolved (amongst other items) to report back to Council on next steps associated with the GV Link project if an investor is secured or bypass funding is announced.
- 2019 Lease between GVCE Mooroopna Solar Pty Ltd and Council for the development of a solar farm executed.
- 6 July 2022 Planning permit issued by Minister for Planning for solar farm on GV Link land to the east of Toolamba Road.
- 2022 Council resolved to allocate funding to complete the revised detailed design for GV Link.
- 2023 Completed updated site layout
- 2023 Works Package 1 – Design – Provision of Services
- 2023 Works Package 2 & 3 – Design – Access Enhancement and Stage 1
- 2023 Flood modelling of the proposed development plan for GV Link
- 2023 GV Link Economic Evaluation (Economic Benefit of GV Link Stage 1)
- 2023 GV Link Benefit/Cost Assessment
- 2023 Report from Valuer to confirm the value of land at GV Link to ensure that land prices offered are competitive in the regional and state-wide industrial property market.
- 28 May 2024 Council committed to the sale of land within Stage 1 at GV Link, subject to Commonwealth Government funding of $8.5M being confirmed.
- 13 February 2025 $8.5 m funding from Commonwealth government secured.
- 25 March 2025 Consideration of awarding contract for construction Stage 1