History of GV Link

A history of the GV Link project from 1997 to today.

1997-2002

Initial concept studies and several reports were commissioned to assess feasibility of GV Link along with delegation to seek government support

  • 1997 Council commenced investigation of the feasibility of developing an intermodal terminal in the region.
  • 2001 Report titled Shepparton Freight Hub/Inland Port completed by Logistics Bureau (funded by the then Victorian Department of Infrastructure)
  • 2002 Report titled Goulburn Valley Freight Logistics Study Phase 2 undertaken by the Logistics Bureau to study the commercial viability of GV Link with respect specifically to SPC-Ardmona.

2003-2011

Commencement of the planning/design process, land acquisition, and feasibility 

  • 18 December 2003 Planning Scheme Amendment C34 to facilitate the establishment GV Link (then known as Goulburn Valley Freight Logistics Centre) placed on exhibition  
  • 2004 Delegation of local industry, Council and government officials visited Canberra to seek Federal support for GV Link
  • 15-17 & 24 June 2004 Panel held. 
  • November 2004 Panel report provided recommending that Planning Scheme Amendment C34 be adopted subject to several recommendations. 
  • 7 December 2004 Council adopted Amendment C34.
  • 5 May 2005 Planning Scheme Amendment C34 approved  
  • 2005 Council commenced an ‘Expression of Interest’ process aimed at securing a preferred developer for the site. 
  • 2007 Economic review of the feasibility of developing the site was undertaken. 
  • 12 December 2008 Development plan and planning application in relation to the subdivision and development of the land issued.
  • 2008 Council undertook ‘Expression of Interest’ for the detailed design of the infrastructure/subdivision plan of the site.
  • 2009 Landscape design report completed 
  • 2010 Detailed design plans completed 
  • 2010 Flood modelling updated 
  • 2011 Council secured the site, finalised payment for the compulsory land acquisition
  • 2013 Economic feasibility review of the GV Link project undertaken

2014 to now

Further review, recent activity, and investor interest 

  • 2014 Council resolved (amongst other items) to report back to Council on next steps associated with the GV Link project if an investor is secured or bypass funding is announced.
  • 2019 Lease between GVCE Mooroopna Solar Pty Ltd and Council for the development of a solar farm executed.
  • 6 July 2022 Planning permit issued by Minister for Planning for solar farm on GV Link land to the east of Toolamba Road.
  • 2022 Council resolved to allocate funding to complete the revised detailed design for GV Link.
  • 2023 Completed updated site layout
  • 2023 Works Package 1 – Design – Provision of Services
  • 2023 Works Package 2 & 3 – Design – Access Enhancement and Stage 1
  • 2023 Flood modelling of the proposed development plan for GV Link        
  • 2023 GV Link Economic Evaluation (Economic Benefit of GV Link Stage 1)
  • 2023 GV Link Benefit/Cost Assessment 
  • 2023 Report from Valuer to confirm the value of land at GV Link to ensure that land prices offered are competitive in the regional and state-wide industrial property market.
  • 28 May 2024 Council committed to the sale of land within Stage 1 at GV Link, subject to Commonwealth Government funding of $8.5M being confirmed.
  • 13 February 2025 $8.5 m funding from Commonwealth government secured.
  • 25 March 2025 Consideration of awarding contract for construction Stage 1