Posted on Monday 4th of April, 2016,
Work is continuing on the new SAM project with the governance model, a Federal Government funding application and a design competition all underway.
Governance Model
A workshop with councillors, the Project Board and other key stakeholders was held to discuss all the options for governance of the new SAM. As a result the Project Board has engaged Russell Kennedy lawyers to provide Governance direction for a Company Limited by Guarantee. This is the only effective way for Council to share the expanded operating risks of a new Art Museum, and to secure capital and operating funds required if the project is to be feasible. The Council cannot deliver the project on its own.
SAM will be governed by a skills based Board on which Council will have two nominated representatives. It recommends the Board comprise individuals with designated skills relevant to a significant cultural institution, able to assist the Governance Board in its objectives.
The new SAM is contingent upon this governance model, the project cannot otherwise be realised, as the private funds required would be unable to be raised under an alternative model.
It is recommended the existing collection remain in the ownership of the Council as will the new building which will be leased to the Art Museum Board for a peppercorn rent. The Art Museum Board may also accept and own works of art, which will enable gifts to the Museum which would otherwise not occur, with private donors often unwilling to give art to a local government entity.
The draft constitution of this new Company Limited by Guarantee will be presented to Council in April.
Funding Applications
Council was successful in obtaining $10m in funding from the Victorian State Government through the Regional Infrastructure Fund as announced on 3 March 2016 by Jaala Pulford, Minister for Regional Development. An application to the Federal Government’s National Stronger Regions Fund was submitted on 15 March 2016.
Capital Contribution
Operational Contribution/Trust Fund
The SAM Foundation will raise the $8m as an endowment to support operating costs. The total capital cost for a new SAM is $34.5m.
Council will then own an asset three times the value of Council's contribution which will generate $58.1m in economic activity over the two year construction period, equating to the creation of 72 direct jobs and a total of 181 jobs including all direct, industrial and consumption effects, across the region.
The SAM Foundation have confirmed funds of $2m and are confident of securing the additional funds. The SAM Foundation ‘Giving Tree” has already secured around $25,000 from community donations and is still growing.
Architectural Design competition
The Project Board is currently working on a Procurement Plan for the architectural design of the new Shepparton Art Museum. This is a two stage competition that will be conducted in accordance with the Australian Institute of Architects' Competition Guidelines and endorsed by the Institute. The design competition will start with an Expression of Interest which will ask for a design approach and a vision for the new facility as well as a capability statement.
From the expression of Interest, a shortlist of architectural firms will be asked to submit a concept design for consideration.
The management of the design competition and the full design phase will be overseen by a panel of experts including the formal position of a Competition Advisor.
Site Location at Victoria Park Lake
The new SAM will be built adjacent to Victoria Park Lake on land vacated by the Shell Service Station and the Lake Cafe whose leases expire in May 2017. An environmental audit has been conducted with EPA involvement and once the site is vacated remediation works will begin.
The plan to create an elevated building, with a reduced footprint at the site of the existing Shell Service Station on Victoria Park Lake has been endorsed by the Catchment Management Authority. VicRoads are advising on entry and exit points for vehicles.
Construction Phase
Once the design competition is finalised and there is an approved design, building permits and preliminary works can begin. The project is estimated to be a two year build from start to finish.
If you would like to read about the project follow our Tumblr blog for the latest news. http://yournewartmuseum.tumblr.com/
More News from Greater Shepparton
Thursday 26th of February,
Damage at Tatura Skate Park
Council is extremely disappointed by recent damage inflicted on key structures at the new Tatura Skate Park, with sections of the facility now closed as a result. Read more
Thursday 26th of February,
Upcoming night watermain works – Midland Highway and Toolamba Road
Council wishes to advise residents and motorists of changed traffic conditions and reduced speed limits in Mooroopna, due to upcoming night works. Read more
Thursday 26th of February,
Last chance to provide feedback on access and inclusion within Greater Shepparton
Greater Shepparton City Council is reminding the community that time is running out to provide feedback on the development of the new Universal Access and Inclusion Plan 2026–2030, with the community survey closing this Saturday 28 February 2026. Read more
Thursday 26th of February,
Donate pre-loved boots and help local kids stay in the game
Council is inviting the community to donate pre-loved football boots to help local families ahead of the winter sports season. Read more
Thursday 26th of February,
Celebrating International Women’s Day 2026 with flowers, food and community connection
Council will mark International Women’s Day 2026 with a community celebration at the McIntosh Centre in Shepparton, alongside a series of supported local events across the municipality. Read more
Wednesday 25th of February,
Pedestrian crossing upgrade – Marungi Street, Shepparton
Council wishes to advise that upgrade works to the existing pedestrian crossing at the south end of Marungi Street in Shepparton, outside the Shepparton Library, will be commencing on Friday 27 February 2026. Read more
See All News
Want to get the latest news and events in your Facebook feed?
Just go to our Facebook page and click the Like button.
More Events in Greater Shepparton
Sunday 1st of March,
TatFest 2026 - CANCELLED
A festival of food, activities, entertainment and fun for the Tatura and surrounding communities. Opens at 10am and closes at 4pm. Entry, activities and entertainment are free. Read more
Saturday 28th of February,
Swim for Charity: Join the 100 Lap Challenge in Tatura! - Copy
Are you ready to make a splash for a good cause? Dive into the 100 Lap Challenge, an annual charity event held at the Tatura Swimming Complex. Funds raised go directly towards supporting the Tatura Hospital… View on Aquamoves
Saturday 28th of February,
Pedal Boats
Grab a friend and take a pedal boat for a spin. Read more
Friday 27th of February, – to Saturday 28th of February,
Summer City Market 2026
Enjoy two vibrant days of shopping, summer sales, market stalls, entertainment and family fun at the Maude Street precinct in Shepparton CBD. Read more
Thursday 26th of February,
Twilight Tennis - Goulburn Valley Young Professionals
Join the Goulburn Valley Young Professionals for a casual Twilight Tennis Social at the Shepparton Lawn Tennis Club on Thursday 26 February from 6:30 PM to 7:30 PM 🎾 Read more
Saturday 28th of February,
George Nelson Shepparton Gift 2026
🎽 George Nelson Shepparton Gift – 28 Feb 2026 Free entry, elite runners, and a fun Little Athletics community day. Celebrate culture, speed, and community spirit in the Goulburn Valley. Bring the family… Read more
See All Events