Posted on Wednesday 21st of February, 2018,
Greater Shepparton City Council last night endorsed a proposal to use capital works funds rather than take out a loan for the building of the new Shepparton Art Museum with a new estimate of $39.9m for the project.
Two cost reviews during the detailed design phase have revealed that to build to the current budget would result in the new SAM building having limited functionality and requiring further future investment to be operational. The project is consistent with the 2014 business case, competition guidelines and awarded design; there have been no changes to the business case concepts for the project.
The Functional Design Option estimate for the new Shepparton Art Museum project is $39.9m; previous costings were $34.5m. This is an increase of $5.35m. The SAM project was endorsed in May 2015 under the provision that Council would undertake a loan of $10m to fund the project. Financial modelling indicates the project can be funded through existing cash reserves rather than a loan.
Council’s contribution increase to $5.35m in upfront capital would be partially offset by an estimated $4.23m savings in loan interest expense.
The Business Case is four years old and during that period construction costs have risen greater than inflation (4 per cent predicted for this financial year). Environmental systems for art museums are complex and tailored for the building which has increased the project costs.
This is a significant building for Greater Shepparton and in order to have the functionality required for an international standard art museum there is no ability to compromise on design and fit out.
The tender for construction will go out in August 2018 and there is a contingency built into the $39.9m project budget to allow for variations, which is standard practice for any construction project.
While the increase is within accepted parameters for Council, to fund the increase, additional measures to potentially offset this financial risk will be explored such as selected grants for components of the project and changes to the SAM Foundation Capital Works/Trust contribution breakdown.
The 2018/2019 financial year project bid process will not be affected by the SAM capital requirements.
Background information
At the 19 May 2015 Ordinary Council meeting, Council agreed to:
Funding achieved
Successful funding applications from:
Funding in progress
Timelines*
April 2017: Council resolved to appoint Denton Corker Marshal Architects to prepare the necessary detailed design based on the project objectives adopted by Council.
September 2017: SAM site incorporated planning amendment approved
February 2018: Demolition works commence
March 2018: Detail design completed
August 2018: Construction design completed
Late 2018: Build commences
September 2020: Project completion
(*timelines subject to change)
More News from Greater Shepparton
Wednesday 4th of February,
Temporary road closure - Lenne Street, Mooroopna
Greater Shepparton City Council would like to advise that construction of the stormwater rising main will begin along Lenne Street, Mooroopna on Thursday 5 February 2026. Read more
Wednesday 4th of February,
A Wonder Filled Summer delivers festive fun and local winners
Greater Shepparton City Council has announced the winners of its Christmas campaign delivered as part of A Wonder Filled Summer, which featured festive activities, events and installations across the region. Read more
Wednesday 4th of February,
KidsTown future improvements to begin
Greater Shepparton City Council is advising the community that future improvement works will now begin at KidsTown Adventure Playground, located on the Midland Highway (Causeway) in Mooroopna. Read more
Tuesday 3rd of February,
Mark your calendars for the 2026 Summer City Market
Greater Shepparton City Council is inviting community members and visitors to save the date and get ready for two vibrant days of shopping, entertainment and family fun at the Summer City Market on Friday 27 and Saturday 28 February 2026. Read more
Monday 2nd of February,
Sod turned on new Princess Park WB Hunter Pavilion
The first sod was officially turned on the new Princess Park WB Hunter Pavilion today, marking the beginning of the new facility which will serve generations of grassroots sporting players and supporters to come. Read more
Monday 2nd of February,
Nominations now open for the 2026 Greater Shepparton Women’s Awards
Nominations are now open for the 2026 Greater Shepparton Women’s Charter Awards, celebrating the achievements, leadership and community impact of local women across the region. Read more
See All News
Want to get the latest news and events in your Facebook feed?
Just go to our Facebook page and click the Like button.
More Events in Greater Shepparton
Sunday 8th of February,
Peppermill Auction Fundraiser
Supporting the Longwood Community and the Shepparton CFA. Read more
Monday 9th of February,
Family History Chat at Shepparton Library
Family history buffs come and chat! Read more
Wednesday 11th of February,
Puff Walk
Enjoy the beauty of our local parks on Puff Walk! Read more
Tuesday 10th of February,
Special Movie Screening - In the Shadow of the Gallows at Shepparton Library
Special Film Screening (MA 15+). Read more
Monday 9th of February,
Starting Your Small Business - Live Webinar
Learn the essentials of establishing a small business and planning for success. Read more
Sunday 8th of February,
Kuma Entertainment & Lenny's Raves present Lenny's Toddler Techno Tour 2026
In 2026, Lenny Pearce is bringing his globally renowned Toddler Techno Tour back home! View on Riverlinks
See All Events