Lenne Street Drainage Project Update

Council would like to provide an update on the Lenne Street Mooroopna Drainage Upgrade project.

  • Boring works along Lenne Street and Toolamba Road as well as under the railway line have been completed with the stormwater rising main now 80% complete.
  • Lenne Street is closed between Toolamba Road and Howe Street until the end of March while the connection of the stormwater rising main works are completed and the asphalt works are undertaken.
  • The remaining earthworks of the basin will commence mid-March and will take approximately 4 weeks to complete including the linking of the stormwater system to the new pumpstation location.

 